A roll-out schedule sets out which team works at which site and when, how the material gets there and how each site is handed over. Just as important is what it says about things going wrong. That's why we plan with a buffer of around 20 % and agree before the start who decides what on site. Some sites won't be ready when the team arrives. That happens on every roll-out, so it goes into the schedule from the beginning.
What a roll-out schedule covers
In a roll-out, the same or a similar fit-out is installed at many sites. The schedule is what the client, the suppliers and the installation team all work from. Whether the client provides it or we draw it up together matters less. What matters is that everyone knows who is responsible for what.
What goes into the schedule
- order of the sites and dates
- teams and team size for each site
- deliveries: when, where and who receives them
- measurements: who measures and who is responsible for them
- handover: who signs off and which photos are needed
- rules for when something is missing or not ready
- named contacts on both sides
Measurements: who measures, who is responsible
The measurements are taken either by the client or by the installation company. Whoever measures is responsible for the figures. That should be agreed in writing before the job is awarded. Otherwise the first discrepancy leads to a discussion instead of installation.
Material and deliveries
With many sites, deliveries are a job in their own right. On large roll-outs we recommend giving them to a logistics company that delivers the material just in time straight to the stores. We agree the dates with them, so the goods are there when the team arrives. Smaller quantities we can also store in our own warehouse.
If material is still missing, you need a rule: carry on with what's there, or move the site to a later date. We agree that before the first job.
Pace and teams
We install most roll-outs during the day. We work at night or while the store is trading when the client needs it, for example in supermarkets. The pace depends on the floor area and the scope. On small refits we manage several sites a week, on a complete store more like one or two.
Each team has one or two regular team leads. They know the concept, make decisions on site and are the contact for the store. The teams are made up of our own fitters and regular partner teams.
A buffer instead of optimism
Roll-outs rarely fail because there aren't enough fitters. More often the time was calculated too tightly. So we plan with a buffer of around 20 %. If things go better, that's a gain. If they go less well, it was planned for. The buffer costs a little efficiency. In return, the pace holds even when something goes wrong at one site.
Sites that aren't ready
On every roll-out there are sites where the area isn't prepared when the team arrives. Often the floor isn't finished or another trade hasn't finished yet. That's not unusual. We agree in advance what happens then and who decides on site. There's more on this in Site not ready? Clarify first, decide on site.
Handover
Every site is handed over with photos and a report. The instructions for the fitters have to be simple: which photos are needed in which situation. The simpler the instructions, the more complete the record.
What this looks like on a large roll-out is shown in our report on 50 discount stores in Austria.
Planning a roll-out? Send us the number of sites, the timeframe and the scope. We'll check dates and capacity and draw up the schedule with you.
Tell us about your project